Employer :METROPOLITAN MUNICIPALITY OF ISTANBUL
Project Value :
USD 2.884.506.-
Description of the project:
 The works we had completed within the estimation which took place under our undertakings:
 1- Sisli Galataderesi Street, Zincirlidere Street, Dere Street, Salih Tozan Street, Villa Street, Maslak Ahi Evren Street’s Ø500 - Ø2400 diametered 4200m. of rainwater and grid sub-construction
 2- Sisli Galataderesi Street, Salih Tozan Street, Villa Street, Büyükdere Street, Maslak Ahi Evren Street, Dere Street’s Ø200 - Ø600 diametered 3100m. of wastewater construction.
 3- Maslak Hadimköy Forrest Road’s rainwater wastewater productions and sub-base fillings are completed.
 4- Rainwater and wastewater project production is completed on 31.01.1999
Â





Arrangement Work of Various Main Artery Roads and Squares in Europian Side of Istanbul